Stock Markets February 11, 2026

TD Cowen Lowers NuScale Power Rating, Cites Romania SMR Vote as Potential Catalyst

Brokerage flags shifted commercial terms and delayed start dates for Doicesti small modular reactor as sources of added execution risk

By Priya Menon
TD Cowen Lowers NuScale Power Rating, Cites Romania SMR Vote as Potential Catalyst

TD Cowen downgraded NuScale Power to Hold from Buy, pointing to the possibility of a negative outcome from an imminent Nuclearelectrica shareholder vote on the Doicesti SMR project in Romania. While the broker still expects the project to proceed, revised approval conditions transfer more performance and financial risk onto NuScale and push the expected commercial start for the first module into mid-2033, with full plant operation delayed to late 2034.

Key Points

  • TD Cowen downgraded NuScale Power from Buy to Hold due to risk tied to an imminent Nuclearelectrica shareholder vote on the Doicesti SMR final investment decision.
  • Revised approval terms shift greater performance and financial risk onto NuScale and move the expected first-module commercial start to July 2033, with full plant operation by December 2034.
  • Doicesti is currently the only project in FEED using NuScale technology, making it a crucial test case for NuScale's commercial model; an earlier U.S. FEED-stage project was later cancelled.

TD Cowen has revised its recommendation on NuScale Power, moving the stock from Buy to Hold. The change reflects heightened risk linked to an upcoming shareholder vote at Nuclearelectrica - the Romanian state-controlled utility that is the customer for NuScale's small modular reactor (SMR) project at Doicesti. Nuclearelectrica is scheduled to vote on the project's final investment decision on Feb 12-13.

Although TD Cowen still expects the Doicesti SMR project to advance, the brokerage says recently negotiated approval terms place more responsibility on NuScale for module performance and shift the likely timeline for commercial operations. Under the updated schedule provided to investors, the first NuScale Power Module is now forecast to enter commercial operation in July 2033, with the entire six-module plant expected to be online by December 2034. The project had previously been discussed as targeting a 2030 start.

TD Cowen highlighted that Doicesti is presently the only project in active front-end engineering and design (FEED) that is using NuScale technology. That status gives Doicesti particular significance as a test of NuScale's commercial viability, the brokerage said, noting that an earlier U.S. project which reached a similar FEED stage was later cancelled.

The revised commercial terms outlined by TD Cowen include two possible procurement structures. In one scenario, the Romanian project company would acquire the first NuScale Power Module while NuScale would remain responsible for the remaining five modules until the initial unit reaches full operation. In the alternative scenario, the purchaser would buy all six modules up front but NuScale would be contractually required to reimburse the cost of five modules if the first module fails to perform as designed. TD Cowen observed that the increased exposure appears to be concentrated on the reactor modules themselves rather than on the broader plant construction scope.

On the company's short-term finances, TD Cowen assessed the impact as limited. NuScale reported roughly $750 million in cash and investments at the end of its third fiscal quarter, preceding an updated at-the-market financing facility announced in November. Separately, NuScale remains contractually obligated to pay Entra1 $495 million under an earlier milestone agreement.

Given the early stage of NuScale's commercial deployment and the new contractual dynamics with Doicesti, TD Cowen declined to publish a price target for the company. The brokerage warned that while near-term financial exposure is modest, the added performance risk tied to the initial module could become materially significant if that unit does not operate to specification.


Key dates and numbers from TD Cowen's assessment:

  • Nuclearelectrica shareholder vote on Doicesti final investment decision - Feb 12-13.
  • First NuScale module commercial operation - expected July 2033.
  • Full plant commercial operation - expected December 2034 (previously discussed target: 2030).
  • NuScale cash and investments at end of Q3 - about $750 million.
  • Obligation to Entra1 tied to earlier milestone agreement - $495 million.

Risks

  • A negative shareholder vote at Nuclearelectrica could act as a catalyst that adversely affects NuScale's prospects - impacts nuclear technology suppliers and utility project pipelines.
  • Added contractual exposure for NuScale on module performance could create material operational and financial risk if the first module fails to meet design specifications - affects NuScale's module manufacturing and warranty liabilities.
  • Delays in the project timeline from a previously discussed 2030 start to mid-2033/late-2034 could influence revenue recognition and backlog conversion, with implications for capital markets and investor expectations.

More from Stock Markets

Supreme Court to Clarify Reach of Helms-Burton Act in Multi-Billion Dollar Cuba Claims Feb 22, 2026 Switzerland Pulling Ahead in Early Economic Gains from AI Feb 22, 2026 Nvidia Results and Software Earnings to Test AI-Driven Market Sentiment Feb 22, 2026 Analysts Shift AI Bets: Nvidia, Amazon, Dell, Analog Devices, Shopify See Upgrades and Bullish Casework Feb 22, 2026 Investors Trim Positions in EssilorLuxottica Amid Smart-Glasses Threat Feb 22, 2026